Controversies surrounding the Adani power deal have resurfaced, but less attention has been given to the SS Power plant, owned by a private Bangladeshi group, despite its high costs. In FY 2023-24, SS Power’s capacity was only utilized at 21%, yet it incurred a Tk 3,288 crore capacity charge. Ramphal Power Plant, with 24% utilization, faced a Tk 2,237 crore charge. Other plants like Barishal Electric (30%), Payra (65%), and Adani’s (61%) also reported high capacity charges, with Adani costing Tk 5,392 crore. Overall, five coal-based plants incurred Tk 15,686 crore in capacity charges. Payra was the most cost-effective, with a production cost of Tk 11.88 per unit, while Adani’s cost was Tk 15.14 per unit due to higher coal prices.