Rampal plant’s Unit-1 starts power production

Industry: Energy & Power, Power
Industry Intelligence Tag: Industry insights

After being shut down for a month due to a coal shortage, the 1320 MW Rampal power plant’s first unit will start producing electricity again today.

According to BIFPCL, a ship carrying 30,000 tonnes of coal arrived in the country on February 9 and a second shipment carrying 50,000 tonnes is scheduled to arrive on February 18.

The Bangladeshi and Indian governments collaborated to build the Rampal Power Plant. On December 17 of last year, the mega power plant’s first unit started producing 660 MW of electricity on a commercial basis.

 

 

Source for more details:

The Business Post

Dhaka Tribune

Daily Sun

The Business Standard

 

 

 

Source for more details:

Related News

Govt Cancels Excelerate Energy LNG Plant Agreement

October 17, 2024

The interim government has opted not to proceed with an agreement with US-based Excelerate Energy for a new regasification plant for liquefied natural gas (LNG), following the cancellation of a similar deal with Summit Group for a third floating storage and regasification unit (FSRU).

Desco Posts Tk 505.7 Crore Loss for FY24

October 17, 2024

Dhaka Electric Supply Company Ltd (Desco) reported a loss of Tk 505.7 crore for FY24, its second consecutive year in the red. The loss per share improved to Tk 12.7 from Tk 13.61 in FY23, thanks to higher distribution revenue and lower foreign exchange losses.

Excelerate Energy Commits to Further Investment in Bangladesh

October 17, 2024

Excelerate Energy, a US-based company, plans to increase its investments in Bangladesh's energy sector and decarbonization efforts, said CEO Steven Kobos. In a meeting with Chief Adviser Professor Muhammad Yunus, Kobos reaffirmed Excelerate’s commitment to enhancing LNG supply, noting that its two offshore regasification units already provide 34% of the country’s daily gas needs.

Energy Directive Halts Bangladesh’s First LNG Terminal Project

October 15, 2024

Bangladesh's first permanent land-based LNG terminal project has stalled after the Rupantorito Prakritik Gas Company Ltd (RPGCL) canceled the short-listing of bidders due to an interim government directive to halt all energy project negotiations.

Karnaphuli Gas Withholds Tk3,000 Crore from Kafco Sales

October 15, 2024

Karnaphuli Gas Distribution Company has withheld Tk3,000 crore from gas sales to Kafco over 13 years, defying orders to transfer the funds to its parent, Petrobangla. This accumulated amount comes from charging Kafco a higher gas rate than the state-owned fertiliser companies pay.

Govt Accelerates SPM Project After Oil Tanker Fires

October 15, 2024

Following two fire incidents on oil tankers, the government is expediting the implementation of a Single Point Mooring (SPM) with a Double Pipeline to reduce reliance on oil tankers. The fires occurred on the Banglar Jyoti and Banglar Sourav tankers in late September and early October, prompting the Bangladesh Petroleum Corporation (BPC) to fast-track SPM operations, which will streamline crude oil transport to the Eastern Refinery Limited (ERL).

Related News

Govt Cancels Excelerate Energy LNG Plant Agreement

October 17, 2024

The interim government has opted not to proceed with an agreement with US-based Excelerate Energy for a new regasification plant for liquefied natural gas (LNG), following the cancellation of a similar deal with Summit Group for a third floating storage and regasification unit (FSRU).

Desco Posts Tk 505.7 Crore Loss for FY24

October 17, 2024

Dhaka Electric Supply Company Ltd (Desco) reported a loss of Tk 505.7 crore for FY24, its second consecutive year in the red. The loss per share improved to Tk 12.7 from Tk 13.61 in FY23, thanks to higher distribution revenue and lower foreign exchange losses.

Excelerate Energy Commits to Further Investment in Bangladesh

October 17, 2024

Excelerate Energy, a US-based company, plans to increase its investments in Bangladesh's energy sector and decarbonization efforts, said CEO Steven Kobos. In a meeting with Chief Adviser Professor Muhammad Yunus, Kobos reaffirmed Excelerate’s commitment to enhancing LNG supply, noting that its two offshore regasification units already provide 34% of the country’s daily gas needs.

Energy Directive Halts Bangladesh’s First LNG Terminal Project

October 15, 2024

Bangladesh's first permanent land-based LNG terminal project has stalled after the Rupantorito Prakritik Gas Company Ltd (RPGCL) canceled the short-listing of bidders due to an interim government directive to halt all energy project negotiations.

Karnaphuli Gas Withholds Tk3,000 Crore from Kafco Sales

October 15, 2024

Karnaphuli Gas Distribution Company has withheld Tk3,000 crore from gas sales to Kafco over 13 years, defying orders to transfer the funds to its parent, Petrobangla. This accumulated amount comes from charging Kafco a higher gas rate than the state-owned fertiliser companies pay.

Govt Accelerates SPM Project After Oil Tanker Fires

October 15, 2024

Following two fire incidents on oil tankers, the government is expediting the implementation of a Single Point Mooring (SPM) with a Double Pipeline to reduce reliance on oil tankers. The fires occurred on the Banglar Jyoti and Banglar Sourav tankers in late September and early October, prompting the Bangladesh Petroleum Corporation (BPC) to fast-track SPM operations, which will streamline crude oil transport to the Eastern Refinery Limited (ERL).

BUSINESSMONITOR

Connect with


Dont Have Account? Please register Here